September 17, 2010 Update
.
Excavation of the cofferdams is now complete and pile installation on the river piers has commenced.
The foundation of Pier No. 4, on the west side of the Mississippi river, has been poured and work on the above ground portions will begin shortly.
Excavation of Super America site (Lowry Avenue/Marshall St)
|
|
Visitors to the Edgewater Park will remember the paving with the names of the Northeast neighborhoods. These stones were recovered from the park and will be reused in the new park design.
|
|
Information about the open house held on Tuesday March 23, 2010 can be found on the
Get Involved
page.
Residents can learn more about the construction details and schedule at an open house scheduled for Tuesday March 23, 2010 at 6:30pm, where residents can talk with Hennepin County and Lunda Construction Inc. staff, The meeting will be held at the Eastside Neighborhood Center. Check the
Get Involved
page for more information on Public Meetings.
Cofferdam structures for both river piers are now installed. The contractor is excavating material within these cofferdams to allow pile installation. Local residents will now hear the “sounds of construction” as the contractor begins to install the river pier foundation piling. Each pile is 32” in diameter and will extend well over 100’ below the river surface. If placed end to end, the piling supporting the river piers will almost total two miles in length!
Photos of setting the Cofferdam:
|
|
|
|
Construction Fencing along the old SuperAmerica site (Lowry Avenue/Marshall St.)
|
|
Work activity on the West shore includes the excavation of the "Pier No. 4" foundational work and installation of 16" diameter piles.
The East shore work includes the demolition of the "SuperAmerica" store at the corner of Marshall Street/Lowry Avenue that is now completed to make way for an underground water treatment structure.
Excavation of material, along the East slope, continues for East Abutment foundation installation.
After extensive input from the community, residents can look forward to a new Lowry Avenue Bridge with:
- A basket-handle steel arch design that spans more than 400 feet across the navigational channel of the Mississippi River.
- Expanded sidewalks with unobstructed views of the Mississippi River.
- A high efficiency LED lighting system for the steel arch that is color adjustable.
- An anti-icing system that senses the conditions for icing and automatically disperses a measured amount of anti-icing material across the surface. This system can also be remotely controlled from the county’s Public Works Facility or even a snowplow.
- A new underground stormwater treatment facility called a DC sand filter that serves more than 80 acres of the surrounding community.